TIME
ESTIMATE BASED UPON 2 STOP HYDRO
MEN HAVING CORRECT TOOLS & EQUIPMENT
GENERAL CONDITIONS
| UNLOAD MATERIALS | 4 HRS |
| BUILD SCAFFOLD (IF USED) | 2 HRS |
| HATCH: |
8 HRS |
| SET JACK &
PISTON REMOVE SCAFFOLD |
6 HRS |
| SLING & PLATFORM: |
2 HRS |
| SET PUMP UNIT PIPE OIL LINE |
4 HRS |
| GET PLATFORM RUNNING (TEMPORARY) | 1 HR |
| SET FRONTS: |
10 HRS |
| ELECTRICAL: |
7 HRS |
| INSTALL LEVELING UNIT & CAMS | 2 HRS |
| ASSEMBLE CAB | 8 HRS |
| INSTALL CAR DOOR TRACK |
6 HRS |
| PIPE & PULL WIRE: |
4 HRS |
| HOOK UP WIRING: |
8 HRS |
| RUN CAR AUTOMATIC |
4 HRS |
| INSPECTION & PULL OFF JOB | 4 HRS |
| TOTAL | 80 HRS |
|
ADD - 12 HRS PER EACH ADDITIONAL OPENING
|
|